New Largo Offloading Facility

A dedicated coal truck-offloading facility feeding pre-certified coal into the Kusile stockyard — 1 378 m of conveyor, two 100 t tipping stations, a continuous sampling station and an audit bin, delivered under a single contract.

Client

WBHO

Consultant

LSL Consulting

Period

Oct 2023 — May 2025

Location

Mpumalanga, South Africa

01Scope of work

Project management, procurement, fabrication, erection and installation of structural, mechanical and plate work

ClientWBHO
ConsultantLSL Consulting
Contract start23 October 2023
Target completion13 May 2025
First Coal5 December 2024
End userKusile stockyard

Coal truck-offloading facility feeding the Kusile stockyard

MTI Engineering was awarded a contract for the project management, procurement, fabrication, erection and installation of the structural, mechanical and plate work components of the New Largo offloading facility — a dedicated coal truck-offloading facility feeding pre-certified coal into the Kusile stockyard.

The project was executed in collaboration with the design, earthworks, civil and electrical teams, ensuring timely delivery within the allocated schedule. Work commenced on 23 October 2023 with completion targeted for 13 May 2025, including commissioning of the Tariff Sampling Station and the Audit Bin. The 'First Coal' milestone was achieved on 5 December 2024.

The facility is built around three main conveyors totalling 1 278 m, fed by two truck tipping stations of 100 t capacity each. The stations are designed to accommodate coal deliveries by truck operating 16 hours a day, six days a week, 51 weeks a year.

A continuous sampling station was installed on Conveyor 615, supported by a 100 m feed conveyor. An Audit Bin and associated conveyor system were installed on Conveyor 615A to verify mass-meter readings, ensuring accuracy and compliance of the coal tariff measurement.

02System overview

976 m

Conveyor P02-CVY-0615

Main conveyor

145 m

Cross conveyor P02-CVY-0613

Cross-feed

157 m

Conveyor P02-CVY-0615A

Audit bin line

100 m

Sampling feed conveyor

Continuous sampler

2 × 100 t

Truck tipping stations

16 h/day, 6 days/week, 51 weeks/year

Installed

Audit bin

Mass-meter verification

03On site
New Largo Offloading Facility — site photograph 1
New Largo Offloading Facility — site photograph 2
New Largo Offloading Facility — site photograph 3
New Largo Offloading Facility — site photograph 4

Next project — 02

AMV Packing Station V208 Upgrades

Glencore Rhovan

Similar scope?

We have built this before.

If your project looks anything like this one, we have the detailing, the workshop and the erection crews to carry it. Send the scope through.

Vendor pre-qualification

Need our BEE certificate and tax clearance?

Procurement teams can request our current compliance pack — BEE certificate, tax clearance certificate and company profile — and we will send it through the same working day.

Request compliance pack
Call workshopRequest a quote